This project involved the construction of a new foyer, toilets, and associated works within a live facility, with the owner remaining partially in occupation throughout. To minimise disruption, works were carefully staged and coordinated.
Various modifications were carried out, such as the construction of stair access to the Hall mezzanine storage areas, a new Vestry and Storeroom were built within the Sunday School building, relocation of door D12 and wall alterations that involved bricking up openings and raising the Hall’s southern entrance floor to accommodate new double doors. The successful completion of these works has provided the facility with modern, safe, and functional spaces that enhance both usability and comfort for its community.